     We have a huge project with several tasks where I need to add to a timeline the completeness average percentage and, I think, this can be done in single task with this summary of the average percent of the grouped tasks.
     In other words:  I want to filter some tasks (yes/no) to make them appear in the timeline (they have dates) together with the related percentage of completeness.
     I know that I already have the average percentage of completeness in the grid view, when groupping by any field (please check the print screen, where I group the tasks by the field “module”).
     Now I want to show this percentage in the timeline. But how?
     I hope AirTable have it by default…. 🙏 !!!

Print:
1=Avg. % when groupped by module
2=Task (line) where I think the avg % can be included.
3=Timeline where, I think, if I filter by that task, the summary of the groupped tasks will be showed.